It measures the alignment of the initiative with existing policy frameworks in the country. In addition, the scalability of the initiative to other realities and geographies is valued.
Help to restore the country's agricultural capacity in drought stricken are areas through the reduction of vulnerability to hydrologic extreme. Help to restore flood protection in the low-lying areas of the City of Georgetown.
This measures how well the objectives and goals set out in the initiative were fulfilled, as well as the extent to which the results achieved are attributable to the actions implemented by the initiative.
Indicator
Description
Indicator Type
Measure Unit
Base date
Base
Goal
Measure Date
Measure
Compliance
Source
Number of sluices and water control structures
13 sluices and 71 water-control structures were either rehabilitated or constructed throughout key coastal and interior areas.
Effectiveness
Unt
01-01-1970
17
01-01-2002
13
76
World Bank. (2002, August 1). Implementation completion report (No. 24244): El Niño emergency assistance project.
Number of mobile and gravel pumps
The project financed the acquisition of 12 mobile pumps and 7 gravel pumps
Effectiveness
Unt
01-01-1970
13
01-01-2002
19
146
World Bank. (2002, August 1). Implementation completion report (No. 24244): El Niño emergency assistance project.
Number of mobile pumps for the city
The project supported the acquisition of 5 mobile pumps (vs. the two planned) for Georgetown to assist in the pumping of runoff during precipitation occurring during high tide when the sluices have to be closed and the gravity-based drainage system is inoperable.
Effectiveness
Unt
01-01-1970
2
01-01-2002
5
250
World Bank. (2002, August 1). Implementation completion report (No. 24244): El Niño emergency assistance project.
Learned lessons
Gained knowledge from implementing, evaluating, and managing a policy intervention, including why it was or was not effective and how it could be improved in the future.
Lesson
Description
Source
Government commitment to the relief and reconstruction effort
The Government demonstrated early commitment to the relief and reconstruction effort. Apart from providing access and data to lender and donor agencies, the Presidential Secretariat assumed responsibility for the coordination of assistance programs through the Civil Defence Commission.
World Bank. (2002, August 1). Implementation completion report (No. 24244): El Niño emergency assistance project.